February 20 - All hands were at the ready installing the steel frame for the floor to ceiling glass

Galileo’s Pavilion
Construction Photography

comment 0
architecture, architecture, educational, photography

For my final year at the University of Kansas School of Architecture, Design, and Planning, I was a part of Studio 804. The program involves students in all aspects of the building process, from initial design to finished construction. This makes for an exhaustive 10 month experience that allows students to understand and address in a physical way critical issues of sustainability, energy efficiency, and accessibility.

The project that I and 16 other grad students were a part of for 2011-2012 was Galileo’s Pavilion at Johnson County Community College in Overland Park, Kansas. The building is composed of two classrooms and a student lounge that form a courtyard around a pre-exisitng sculpture, Galileo’s Garden. The project is 804’s fifth LEED Platinum project.

I was fortunate enough to be the one that took the photos that show the breadth of this work, which ranfrom the beginning of January 2012 through completion in time for a June 21 open house.

 

2012_STUDIO804_CONSTRUCTION_001

Studio 804 participants.

January 12 - Concrete foundation formwork goes in despite the cold weather and snow

January 12 – Formwork for the concrete foundation goes in despite the cold weather and snow

January 13 - Concrete being poured into the formwork

January 13 – The pour

January 16 - Foundation concrete has cured enough for the formwork to come off

January 16 – Foundation concrete has cured enough for the formwork to be removed

January 16 – Gravel that will form the base of the crawlspace concrete floor is poured in

Participants work late into the evening installing the crawlspace vapor barrier and 6" layer of XPS insulation

January 16 – Participants work late into the evening installing the crawlspace vapor barrier and 8″ layer of EPS insulation

January 20 - Crawlsapce concrete floor is poured

January 20 – Crawlsapce concrete floor is poured

January 21 - Work begins on refilling the excavated areas around the foundation.

January 21 – Work begins on refilling the excavated areas around the foundation.

January 23 – Expansion joints are cut into the concrete

January 30 - Installation of the floor joists is finished.

January 30 – Installation of the floor joists is finished.

February 01 - Wall blocking is installed on top of floor sheathing

February 01 – Wall blocking is installed on top of floor sheathing

February 02 - Plastic barrier and rebar are installed for concrete floor

February 02 – Plastic barrier and rebar are installed for concrete floor

2012_STUDIO804_CONSTRUCTION_013

February 08 – What will be the finished concrete floor–which contains fly ash and a special granite aggregate–is poured

February 14 - Blankets to insulate the concrete while it cures are removed after some snowfall

February 14 – Blankets  to insulate the concrete while it cures are removed after some snowfall

 February 17 - One of the 12" deep walls is lifted into place with a ratchet and pulley system.

February 17 – One of the walls–whose 12″ deep framing will be used to create a super-insulated cavity–is lifted into place

February 18 - Exercising those arm muscles to lift another of the walls into place

February 18 – Exercising those arm muscles to lift another of the walls into place

February 20 - All hands were at the ready installing the steel frame for the floor to ceiling glass

February 20 – All hands were at the ready installing the steel frame for the floor to ceiling glass

February 21 - Taking a break from all the heavy lifting

February 21 – Taking a break from all the heavy lifting

February 22 - All the wall framing is up

February 22 – All the wall framing is up

February 23 - A construction forklift is needed to lift some of the heavier roof structural members into place

February 23 – A construction forklift is needed to lift some of the heavier roof structural members into place

February 23 - Lights from the nearby parking lot cast some late night shadows

February 23 – Lights from the nearby parking lot cast some late night shadows

February 24 - Roof sheathing begins to go up

February 24 – Roof sheathing begins to go up

February 24 – Where it then gets nailed down

February 24 - And again

February 28 – Compressed air made for an easier life with all the nails that were used

March 02 - The weather didn't make for an easier life as the parapet was installed

March 02 – The weather didn’t make for an easier life as the parapet was installed

March 03 - The sloped roof insulation is installed

March 03 – The sloped roof insulation is installed

March 06 – Multiple hands were needed as the EPDM roof membrane was massaged into place

March 10 - The morning sun casts shadows through the plastic used to seal up the window openings

March 10 – The morning sun casts shadows through the plastic used to seal up the window openings

March 16 - Operable skylights with rain sensors allow for cross ventilation in the spaces

March 16 – Operable skylights with rain sensors allow for cross ventilation in the spaces

March 17 - Steel studs for the rain screen and foiled 1" EPS insulation go on over the building wrap

March 17 – Steel studs for the rain screen and foiled 1″ EPS insulation go on over the building wrap

March 17 - A big whole was needed for the 5000 gallon cistern that supplies the interior planted walls with water runoff from the roof

March 17 – A big whole was needed for the 10000 gallon cistern that supplies the interior planted walls with water runoff from the roof

March 23 - Reclaimed slate - mostly from chalkboards salvaged from surrounding schools, were cut to size for the rain screen

March 23 – Reclaimed slate, mostly from chalkboards salvaged from surrounding schools, were cut to size for the rain screen

March 28 - Strings, levels, and plenty of eyeballs were needed to make sure the first courses of slate went in correctly

March 28 – Strings, levels, and plenty of eyeballs were needed to make sure the first courses of slate went in correctly

April 02 - Rock Chalk!

April 02 – Rock Chalk!

April 11 - There was never a lack of dirt that needed to be moved from one spot to another

April 11 – There was never a lack of dirt that needed to be moved from one spot to another

April 16 - Some cleaning required

April 16 – Some cleaning required

April 17 - The floor to ceiling glass was reclaimed from an Kansas City office building that was cancelled midway through construction

April 17 – The floor to ceiling glass was reclaimed from a Kansas City office building that was cancelled midway through construction

April 19 - Steady now!

April 19 – Steady now!

April 25 - Closing it all in

April 25 – Closing it all in

April 18 - Drywall!

April 18 – Drywall!

April 21 - Dryceiling!

April 21 – Dryceiling!

April 21 - Insulation made from recycled newspapers is blown into the wall and ceiling cavities

April 21 – Insulation made from recycled newspapers is blown into the wall and ceiling cavities

May 02 - The last of the glass goes up as the slow process of polishing the concrete floors begins

May 02 – The last of the glass goes up as the slow process of polishing the concrete floors begins

May 08 - Almost too pretty to be walked on

May 08 – Almost too pretty to be walked on

May 08 - Paint it white!

May 08 – Paint it white!

May 11 - Cuts are made to install the first few plants of the 10000 or so that make up the 3 plant walls

May 11 – Cuts are made to install the first few plants of the 10000 or so that make up the 3 green walls

May 05 - Foundations are poured for Dale Eldred's "Galileo's Garden" sculpture

May 05 – Foundations are poured for Dale Eldred’s “Galileo’s Garden” sculpture

May 24 - Formwork is put in place for the courtyard retaing walls

May 24 – Formwork is put in place for the courtyard retaining walls

May 30 - Formwork is finished and ready for concrete

May 30 – Formwork is finished and ready for concrete

June 02 - The first of the frosted glass louvers are installed, with only 591 more to follow

June 02 – The first of the frosted glass louvers are installed, with only 591 more to follow

June 11 - Getting close

June 10 – Interior view of a few of those 591 louvers set in place

A few of those 591 louvers set in place

May 10 - All exterior work, including the installation of the wind turbine, nears completion

June 10 – Most of the  exterior work, including the installation of the wind turbine, nears completion

June 13 - Sod begins to go down

June 13 – Sod begins to go down

June 15 - Custom light fixtures composed of plate steel and fiber optics before installation onto the ceiling

June 15 – Custom light fixtures composed of plate steel and fiber optics before installation onto the ceiling

June 18 - While pretty, the weight of these light fixtures did not make for an enjoyable installation

June 18 – While pretty, the weight of these light fixtures did not make for an enjoyable installation

June 18 - The June 21 open house required us to put in some late hours to tidy some final details up

June 18 – The June 21 open house required us to put in some late hours to tidy some final details up

June 21 - All done!

June 21 – All done!

Leave a Reply